Andritz to Upgrade Recovery Boiler at Södra Cell's Värö Mill in Sweden
Monday, April 6, 2009 8:51 pm The main components for the recovery boiler upgrade include feedwater pre-heaters, additional air pre-heaters, and one additional super-heater stage to maintain the super-heating level with increased steam flows. The scope of supply also includes air port optimization, and enlarging the economizer to restrict temperature increase of the flue gases due to the elevated feedwater temperature. Andritz also received a follow-up order for the delivery of a flue gas cooler to use the flue gas energy content, which will increase due to the feedwater preheating. Installation work for both projects will be carried out during a shutdown in November 2009. The Andritz Group is a global market leader for customized plants, process technologies, and services for the hydropower, pulp and paper, metals, and other industries (solid/liquid separation, feed, and biofuel). The Group is headquartered in
|